No known major changes have been scheduled for the next 5 days.
Daisy’s full change process has been completed including implementation, test and back-out plans which have been reviewed by senior technical reviewers and management. Please contact the service desk quoting the change number if you have any queries.
Change Number | Type | Impact Statement | Risk Statement | Planned Start | Planned End |
---|---|---|---|---|---|
CHG0166092 | Normal | No impact to service is anticipated during the maintenance window | Services should be considered at risk for the duration of the maintenance window. | 9 July, 2024 9:30 am | 9 July, 2024 12:30 pm |
Change Number | Type | Impact Statement | Risk Statement | Planned Start | Planned End |
---|---|---|---|---|---|
CHG0166491 | emergency | Total loss of service for anticipated impact duration | Services should be considered at risk for the duration of the maintenance window. | 2 July, 2024 8:00 pm | 2 July, 2024 11:59 pm |