Change NumberTypeImpact StatementRisk StatementPlanned StartPlanned End
CHG0161183normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.29 April, 2024 8:00 am29 April, 2024 8:00 pm
CHG0161310normalTotal loss of service for anticipated impact durationServices should be considered at risk for the duration of the maintenance window.25 April, 2024 9:00 pm26 April, 2024 11:00 pm
CHG0154547normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.30 April, 2024 8:00 am30 April, 2024 7:00 pm
CHG0161794normalTotal loss of service for maintenance windowServices should be considered at risk for the duration of the maintenance window.30 April, 2024 11:00 am1 May, 2024 11:00 am
CHG0154551normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.2 May, 2024 8:00 am2 May, 2024 7:00 pm
CHG0154549normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.1 May, 2024 8:00 am1 May, 2024 7:00 pm
Change NumberTypeImpact StatementRisk StatementPlanned StartPlanned End
CHG0161578normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.25 April, 2024 6:00 pm26 April, 2024 2:00 pm
CHG0161451normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.29 April, 2024 9:00 am29 April, 2024 5:30 pm
CHG0161502normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.30 April, 2024 9:00 am30 April, 2024 3:00 pm
CHG0161435normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.30 April, 2024 9:00 am30 April, 2024 4:00 pm
CHG0162013emergencyService degradation for maintenance window durationServices should be considered at risk for the duration of the maintenance window.26 April, 2024 8:00 pm26 April, 2024 10:00 pm
CHG0161915emergencyNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.25 April, 2024 9:00 am25 April, 2024 5:00 pm
CHG0161925normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.2 May, 2024 9:00 am2 May, 2024 1:00 pm
No major changes scheduled
No major changes scheduled
No major changes scheduled
No major changes scheduled
No major changes scheduled
Change NumberTypeImpact StatementRisk StatementPlanned StartPlanned End
CHG0161480normalTotal loss of service for anticipated impact durationServices should be considered at risk for the duration of the maintenance window.25 April, 2024 8:00 am26 April, 2024 8:00 am
No major changes scheduled